{"schema":"hottub-news/story/v1","story":"st_tmlatrrm4sarursnl5za","title":"就高鐵香港段延誤及超支 港鐵向政府支付22.5億元","title_en":"MTR pays the government 22.5 billion yuan for delays and overruns on the Hong Kong section of the high-speed rail","outlets":4,"brief":null,"page":"https://hottub.news/stories/government-and-mtr-reach-agreement-on-shatin-line-mtr-to-pay-hk-22-5-tmlatrrm4s","count":5,"items":[{"id":"n_lmknj2ali3gxyzmngmyq","seq":1381133,"kind":"article","title":"就高鐵香港段延誤及超支 港鐵向政府支付22.5億元","title_en":"MTR pays the government 22.5 billion yuan for delays and overruns on the Hong Kong section of the high-speed rail","url":"https://hk.news.yahoo.com/%E5%B0%B1%E9%AB%98%E9%90%B5%E9%A6%99%E6%B8%AF%E6%AE%B5%E5%BB%B6%E8%AA%A4%E5%8F%8A%E8%B6%85%E6%94%AF-%E6%B8%AF%E9%90%B5%E5%90%91%E6%94%BF%E5%BA%9C%E6%94%AF%E4%BB%9822-5%E5%84%84%E5%85%83-110223203.html","summary":"【Now新聞台】高鐵香港段延誤3年通車，並超支近200億元，政府與港鐵事隔8年達成解決安排，港鐵須向政府支付22.5億元，而同樣延誤及超支的沙中綫則不作追討。 高鐵香港段工程2010年展開，原定2015年通車，因應工程延誤，最終在2018年9月開通，工程造價亦由650億元超支至封頂水平的844億元，港鐵在2015年向立法會申請追加撥款前，宣布向股東派發特別股息，作為大股東的政府收到逾195億元特別股息，政府與港鐵通過多輪磋商，最終港鐵須為工程延誤向政府支付22.5億元。 至於2012年展開的沙中綫，因應宋皇臺站發現遺蹟、會展站地盤出現戰時炸彈、紅磡站擴建工程剪短鋼筋等連串事件，屯馬...","published":"2026-10-02T13:51:33Z","seen":"2026-10-02T15:52:00Z","lang":"zh","country":"HK","source":{"id":"kite-hk-news-yahoo-com-d17f42","name":"hk.news.yahoo.com","domain":"hk.news.yahoo.com","outlet":{"wikidata":"Q22099769","name":"Yahoo! Hong Kong","type":"website","designations":["website"]}},"via":"kite-hk-news-yahoo-com-d17f42","entities":[{"id":"Q14751","name":"MTR","type":"org"},{"id":"Q8646","name":"Hong Kong","type":"place"}],"story":"st_tmlatrrm4sarursnl5za","category":"economy-business","category_p":0.6700000166893005,"sentiment":"negative","tone":-0.4399999976158142,"political":0.5899999737739563},{"id":"n_z5xxojrnklowwcpsgpia","seq":1381134,"kind":"article","title":"就高鐵香港段延誤及超支 港鐵向政府支付22.5億元（楊佩詩報道）","title_en":"MTR pays the government 22.5 billion yuan for delays and overruns on the Hong Kong section of the high-speed rail","url":"https://hk.news.yahoo.com/%E5%B0%B1%E9%AB%98%E9%90%B5%E9%A6%99%E6%B8%AF%E6%AE%B5%E5%BB%B6%E8%AA%A4%E5%8F%8A%E8%B6%85%E6%94%AF-%E6%B8%AF%E9%90%B5%E5%90%91%E6%94%BF%E5%BA%9C%E6%94%AF%E4%BB%9822-5%E5%84%84%E5%85%83-%E6%A5%8A%E4%BD%A9%E8%A9%A9%E5%A0%B1%E9%81%93-135133822.html","summary":"【Now新聞台】高鐵香港段延誤3年通車，並超支近200億元，政府與港鐵事隔8年達成解決安排，港鐵須向政府支付22.5億元，而同樣延誤及超支的沙中綫則不作追討。 高鐵香港段工程2010年展開，原定2015年通車，因應工程延誤，最終在2018年9月開通，工程造價亦由650億元超支至封頂水平的844億元，港鐵在2015年向立法會申請追加撥款前，宣布向股東派發特別股息，作為大股東的政府收到逾195億元特別股息，政府與港鐵通過多輪磋商，最終港鐵須為工程延誤向政府支付22.5億元。 至於2012年展開的沙中綫，因應宋皇臺站發現遺蹟、會展站地盤出現戰時炸彈、紅磡站擴建工程剪短鋼筋等連串事件，屯馬...","published":"2026-10-02T13:51:33Z","seen":"2026-10-02T15:52:00Z","lang":"zh","country":"HK","source":{"id":"kite-hk-news-yahoo-com-d17f42","name":"hk.news.yahoo.com","domain":"hk.news.yahoo.com","outlet":{"wikidata":"Q22099769","name":"Yahoo! Hong Kong","type":"website","designations":["website"]}},"via":"kite-hk-news-yahoo-com-d17f42","entities":[{"id":"Q14751","name":"MTR","type":"org"},{"id":"Q8646","name":"Hong Kong","type":"place"}],"story":"st_tmlatrrm4sarursnl5za","category":"economy-business","category_p":0.550000011920929,"sentiment":"negative","tone":-0.4099999964237213,"political":0.5899999737739563},{"id":"n_f6kde2xo6urjysp5r7oq","seq":1335680,"kind":"article","title":"政府：就廣深港高鐵香港段工程延誤 港鐵將支付22.5億元 沙中線項目雙方不作追討","title_en":"Government: Regarding the delay in the Hong Kong section of the Guangzhou-Shenzhen-Hong Kong High-Speed Railway project, MTR will pay 2.25 billion Hong Kong dollars, the Shatin-Central Line project parties will not pursue compensation","url":"https://www.i-cable.com/%e6%96%b0%e8%81%9e%e8%b3%87%e8%a8%8a/509702/%E6%94%BF%E5%BA%9C-%E5%B0%B1%E5%BB%A3%E6%B7%B1%E6%B8%AF%E9%AB%98%E9%90%B5%E9%A6%99%E6%B8%AF%E6%AE%B5%E5%B7%A5%E7%A8%8B%E5%BB%B6%E8%AA%A4-%E6%B8%AF%E9%90%B5%E5%B0%87%E6%94%AF%E4%BB%9822","summary":"【有線新聞】政府與港鐵達成協議，就高鐵香港段工程延誤，港鐵會向政府支付22.5億元，而沙中綫延誤及工程問題，雙","published":"2026-10-02T11:54:32Z","seen":"2026-10-02T12:03:15Z","lang":"zh","country":"HK","source":{"id":"kite-i-cable-com-d731dc","name":"i-cable.com","domain":"i-cable.com"},"via":"kite-i-cable-com-d731dc","topics":["新聞資訊","港聞","首頁新聞"],"authors":["有線新聞"],"entities":[{"id":"Q14751","name":"MTR","type":"org"}],"story":"st_tmlatrrm4sarursnl5za","category":"economy-business","category_p":0.699999988079071,"sentiment":"positive","tone":0.17000000178813934,"political":0.6600000262260437},{"id":"n_kjhqx5mjrrv4tfizj73a","seq":1326488,"kind":"article","title":"政府與港鐵就高鐵香港段及沙中綫工程達和解 高鐵香港段工程延誤港鐵向政府支付22.5億元 沙中綫項目雙方不作追討","title_en":"Government and MTR reach agreement on High Speed Rail Hong Kong Section and Shatin-Central Link project: High Speed Rail Hong Kong Section project delayed, MTR to pay government HK$22.5 billion; Shatin-Central Link project both parties not to pursue claims","url":"https://www.i-cable.com/%e8%b2%a1%e7%b6%93%e8%b3%87%e8%a8%8a/509675/%E6%94%BF%E5%BA%9C%E8%88%87%E6%B8%AF%E9%90%B5%E5%B0%B1%E9%AB%98%E9%90%B5%E9%A6%99%E6%B8%AF%E6%AE%B5%E5%8F%8A%E6%B2%99%E4%B8%AD%E7%B6%AB%E5%B7%A5%E7%A8%8B%E9%81%94%E5%92%8C%E8%A7%A3-%E9%AB%98","summary":"【有線新聞】政府與港鐵就高鐵香港段及沙中綫工程達成和解，當中就高鐵香港段工程延誤，港鐵向政府支付22.5億元。","published":"2026-10-02T10:25:39Z","seen":"2026-10-02T11:01:37Z","lang":"zh","country":"HK","source":{"id":"kite-i-cable-com-c6a5b2","name":"i-cable.com","domain":"i-cable.com"},"via":"kite-i-cable-com-c6a5b2","topics":["財金總覽","財經資訊"],"authors":["有線新聞"],"story":"st_tmlatrrm4sarursnl5za","category":"economy-business","category_p":0.6600000262260437,"sentiment":"positive","tone":0.10999999940395355,"political":0.550000011920929},{"id":"n_tmlatrrm4sarursnl5za","seq":1326811,"kind":"article","title":"沙中線︱政府與港鐵達成和解 港鐵就高鐵香港段延誤支付22.5億港元","title_en":"Government and MTR reach agreement on Shatin Line: MTR to pay HK$22.5 billion for delay in Hong Kong section of high-speed rail","url":"https://www.stheadline.com/society/3621773/%E6%B2%99%E4%B8%AD%E7%B7%9A%E6%94%BF%E5%BA%9C%E8%88%87%E6%B8%AF%E9%90%B5%E9%81%94%E6%88%90%E5%92%8C%E8%A7%A3-%E6%B8%AF%E9%90%B5%E5%B0%B1%E9%AB%98%E9%90%B5%E9%A6%99%E6%B8%AF%E6%AE%B5%E5%BB%B6%E8%AA%A4%E6%94%AF%E4%BB%98225%E5%84%84%E6%B8%AF%E5%85%83","summary":"政府今日（2日）與港鐵公司就高鐵香港段及沙中線工程項目達成解決安排。港鐵將就高鐵延誤向政府支付22.5億港元；沙中線方面，港鐵先前已承擔約28億元額外開支，雙方同意不作互相追討。政府強調已吸取經驗並加強新鐵路項目的監察，新項目超支等風險將由港鐵全數承擔。 港鐵公司行政總裁楊美珍表示，高鐵（香港段）及沙中綫在早年建造期間，因工程及其他挑戰而引致延誤及相關爭議。港鐵和政府有關部門作出了善後處理的同時，","published":"2026-10-02T10:02:47Z","seen":"2026-10-02T11:05:05Z","lang":"zh","country":"HK","source":{"id":"kite-stheadline-com-b401ae","name":"stheadline.com","domain":"stheadline.com","outlet":{"wikidata":"Q5241255","name":"Sing Tao Daily","type":"newspaper","designations":["daily newspaper"]}},"via":"kite-stheadline-com-b401ae","authors":["author"],"entities":[{"id":"Q14751","name":"MTR","type":"org"},{"id":"Q8646","name":"Hong Kong","type":"place"}],"story":"st_tmlatrrm4sarursnl5za","category":"economy-business","category_p":0.6899999976158142,"sentiment":"neutral","tone":0.0,"political":0.4000000059604645}]}